FUENTE DE FINANCIAMIENTOMONTO % PROPORCIÓN DEL TOTAL COSTO ANTES DE ISRBENEF FISCAL (TASA ISR)COSTO DESP DE ISR CCPP
Prestamo $ 52,700.83 100% 14.50% 5.48% 13.705400% 13.71%
Capital Social $ - 0% 0% 0% 0.00% 0.00%
Suma $ 52,700.83 100% 13.71%
HERRERA
INN INICIAL $ 52,700.83
AÑO
1 $ 35,859.97 $ 1,984.02 5.53%
2 $ 46,617.96 $ 2,672.53 5.73%
3 $ 25,101.98 $ 1,295.51 5.16%
5.48%
HERRERA
INV INICIAL $ 52,700.83
BENFICIO 1 $ 35,859.97 1
FALTANTE $ 16,840.86 1.361252616 AÑOS
4.335031391 MES
10.19053815 DIAS
4.572915675 HORAS
34.37494047 MINUTOS