Massachusetts Institute of Technology

                                                    Building 31 Renovations



































          SIZE                     OWNER
          70,000 square feet       Massachusetts Institute of
          New - 10,000 SF          Technology
          Renovation - 60,000 SF
                                   ARCHITECT
          CONTRACT TYPE            Imai Keller Moore Architects
          Construction Manager-at-Risk





                                                                      PROJECT DETAILS
         Renovations to the Departments of Mechanical Engineering and Aeronautics   •  We will minimize disruptions for users
         & Astronautics will include the creation of more contiguous offi  ce and   occupying the building during construction
                                                                           through intense preconstruction scheduling.
         departmental space, a two-story fl ying robotics lab, a new emergency
         generator, new elevators, improved pedestrian circulation, insulation of lab   •  Building Information Modeling (BIM) will be
         space, new HVAC and electrical equipment and infrastructure upgrades   utilized for 3D coordination of the mechanical
                                                                           systems.
         to meet code, safety and fi re protection requirements. Expansion will
         include new mezzanines and an addition on top of the High Bay area   •  A high standard of sustainability will be met
         in order to meet the Departments’ programmatic needs.             through the use of climate control, recycled and
                                                                           locally extracted and manufactured materials,
                                                                           low-VOC building products, low-fl ow fi xtures
                                                                           and water-effi  cient landscaping. Pursuing
                                                                           LEED certifi cation.
                                                                          •  Precise coordination of shut downs will be
                                                                           necessary in order to tie into existing electrical
                                                                           systems and to synchronize with the adjacent
                                                                           MIT.nano project.
                                                                          •  All lab spaces will remain operational during
                                                                           the course of construction with scheduled shut
                                                                           downs as necessary to accommodate the work.
                                                                          •  Extensive system upgrades and additions
                                                                           within highly congested spaces.