Page 38 - UNIT 4 - CONSTRUCTION OF RIGID PAVEMENT
P. 38
Civil Engineering Department | DCC3113 : Highway & Traffic Engineering
Let’s do this activity
Now, let’s take five and do this activity. Compare the methods of paving rigid CHECK
pavement between manual and mechanical
Manual Mechanical
Set up side form in certain distance of the Set up side form a long distance of the
pavement before paving. pavement before paving.
Cast the concrete by hand (human Cast the concrete by machine as slip paver
labor) and fix pave.
Construction takes a long time Reduce the time of construction period
High labour costs Reduce labour cost
Compacted concrete slab surface use Compaction & forming operations long-run
'Vibrating tamping beam by hand within the term limits of paving machine
Requires the use wooden or metal side
forms that are set up along the perimeter Does not require any steel or wooden forms
of the pavement before paving