Page 44 - UNIT 3 - CONSTRUCTION OF FLEXIBLE PAVEMENT
P. 44

Civil Engineering Department  | DCC3113 : Highway & Traffic Engineering





   Concept                                                        Rolling




          •    Premix Compaction
                –     Consists of:

                      •     Breakdown/initial – smooth wheel, <5km/hr
                      •     Intermediate/principal – pneumatic, <8km/hr, weight ≥15 ton, tyre pressure ≥
                            0.7N/m   2

                      •     Final – smooth wheel, eliminate irregularities, tyre tracks

                –     Temperature at the commencement of rolling ≥110˚C.
                –     Operate longitudinal direction with driven wheels towards the paver, lower to higher
                      edge.

                –     Passes overlapped half width of the roller.
                –     Construction joint cut back straight, brushed on with RS-1K 10-15 minutes before
                      laying of next section, no joints along wheelpaths.

                –     Rollers, heavy vehicles shall not be allowed to stand on newly laid mix before
                      compaction completed and thoroughly cooled & set.













                                                                                                                                   HOME
          Prepared by : SITI ZURAIFA BINTI MD SAH, zuraifa@pmu.edu.my
   39   40   41   42   43   44   45   46   47   48   49