Project Physical Achievement







                                                             Implementation Status Dec 2016
               Item   Project
                                               DJ    IJ    LJ   PT   PS   PDT     Ongoing       TOTAL
                 1    Roads                     2    3     1    3    49    2         9           58                   SUMMARY

                 2    Bridges & Wharves         1    5     1    0     5    0         7           12
                 3    Water Supply              1    1     0    0    22    2         2           24                   2016

                 4    Building                  1    3     1    3    10    0         8           18
                 5    SCORE                     0    1     0    0     9    0         1           10

                             TOTAL              5    13    3    6    95    4        27           122


            DJ  -   Ahead of Schedule
            IJ  -   On Schedule
            LJ  -   Delay
            PT  -   Critical
            PS  -   Completed Project
            PDT -   Terminated