Page 21 - KOP Panborneo Highway Report Card Jan-june 2017
P. 21

progress arial photograph                                                         CH 36+000                    Completed second binder at LHS of
                                                                                                                          carriageway and open to traffic
                                                                                                                          flow. Laying subbase layer at RHS.