Page 39 - Property Rights in the Philippine A Time and Cost Study_July 2017
P. 39
Activity Supporting Docs: Some supporting papers
Secures required supporting Php 2,000.00 take so long to be secured
papers (DPLI assists) and (Depends on the specific (due to cost, distance,
submits to DPLI supporting papers) complication, or adverse
relations) that lot
Because of the perceived occupants tend to
abandon their application
complexity of the process,
many applicants opt for
“Package Deals” which
ranges from PhP 2,000.00
to PhP 15,000.00
PREPARATION OF CARPETA 10 days
COMPLETED STAFF Completed Staff Work
Titling application with • Titling Application Will depend on the
18 complete supporting WORK NA
documents • Final Land Investigation number of submitted
Actor Report applications with complete
LGU-LMO • Barangay Certification documents (the more
31