Opinion of Probable Cost
                                                                                          Birchwood Design Group
                                                                                                Jun-16

          Opinion of Probable Cost - Finn School Mooney Fields

                              Item                Quantity  Unit  Unit Price  Total

              Site Preparation/Demolition
                                      Temporary Utilities  1  LS  $8,000      $8,000
                                Temporary Chainlink Fence  2500  LF  $6      $15,000
                  Remove & Dispose Asphalt Surface Tennis courts  150  SY  $9  $1,300
                                           Silt Sock  2,000  LF    $3         $6,000
                                       Inlet Protection  5  EA    $300        $1,500
                                           Subtotal                          $31,800

              Site Improvements
                                   Roug Grading of Site  1  LS   $25,000     $25,000
                                    Fine Grading of Field  1  LS  $25,000    $25,000
                                      Fencing per field  650  LF  $32        $20,800
                           Natural Grass field ~ 47716 sf @ 6"
                                         Haul in of topsoil  600  CY  $25    $15,000
                                  Infield Soil Amendments  1  LS  $30,000    $30,000
                                              Irrigation  1  LS  $40,000     $40,000
                                           Drainage  1     LS    $25,000     $25,000                                                                                                                                                    SECTION 5 -  RECOMMENDATIONS/ PRIORITIZATION
                                         Seeding per field  1  LS  $3,000     $3,000
                                       Batting Tunnels  4  EA   $9,000.00    $36,000
                            Equipments, bases, foul poles etc  1  EA  $25,000  $25,000
                                          Scoreboard  1    LS    $25,000     $25,000
                                            Dugouts  2     EA    $20,000     $40,000
                                           Subtotal                          $309,800
                                           x4 Fields                        $1,239,200
                                    Lighting of 2 Fields                     $600,000
                        Restroom Press box/central building                  $200,000
                SUBTOTAL OF SITE CONSTRUCTION ITEMS       TOTAL             $1,271,000
             GENERAL CONDITIONS, BOND, CONTRACTOR OH&P                       $127,100
                          CONTINGENCY                                        $63,550
                              TOTAL                                         $3,501,000