                   C. Common Auxiliaries for Refinery and Fractionation

                   1.  Laboratory Equipment

                   2.  Insulation Materials
                   3.  Air Compressor

                   4.  Welding Rods for installation of plant

                   5.  Tools, tackles, workshop equipment for installation of the plant
                   6.  Workshop equipment

                   7.  Manpower for installation of plant consisting of:

                       8 welders and 8 fitters for 5 months
                       1 electrical cum Instrumentation person for 3 months

                       3 insulation persons for 3 months