SEVERAL WIND ENERGY PROJECTS IN SLOW LANE SINCE 2017 AUCTIONS





































                Tamil Nadu Generation and Distribution Company (TANGEDCO) auctioned 500 mw of wind capacity in August 2017.

        BENGALURU: A large number of wind    start commissioning, while only 50 mw has   factory in Rajasthan in 2017 and laid off
        energy projects have been bid out since   been commissioned by Regen Powertech.   about 400 employees. The company has
        auctions for such projects began in early   Leap Green Energy's managing director   almost stopped making turbines and has
        2017, both by Solar Corporation of India   Rajeev Karthikeyan said the project will be   gone into operations and maintenance
        (SECI) and state agencies, but only a small   completed only by May of next year and that   (O&M) only. Through this tender, it will be
        fraction of them have been commissioned so   the company has sought an extension. “From   venturing into operating its own projects for
        far. Out of the 500 mw of wind capacity bid   the time that you get the land and substation   the first time.
        out by Tamil Nadu two years ago, for   built, it takes about seven-eight months to get
        instance, only 50 mw has been        the project working,” he said. “And land has   The PPA has an inbuilt time extension of five
        commissioned so far, according to a senior   been hard to get. There is lot of competition   months after project completion of 15
        state government official.            in the state for land (since it is one of the best   months, with penalty by way of bank
                                             wind producing states in the country.) We   guarantee to an extent of Rs 10 lakh per mw.
        Tamil Nadu Generation and Distribution   have had issues with buying agricultural land   “TANGEDCO has secured Rs 20 crore and
        Company (TANGEDCO) auctioned 500 mw   and converting it.”                 Rs 25 crore respectively from the two
        of wind capacity in August 2017. Regen                                    developers and shall encash the amounts
        Powertech was allotted 200 mw at a tariff of   Founded in 2006, the Tamil Nadu-based   proportionately up to five months,” said the
        Rs 3.42 per unit while Leap Green Energy   company is promoted by Formula 1 driver   official cited earlier.
        got 250 mw at Rs 3.43 per unit. Being the   Narain Karthikeyan's family. It has a
        first wind auction conducted by a state, the   commissioned capacity of 751 mw.   Hence, the winners have time till June to
        tariffs were very low. The power purchase   Queries sent by ET to Regen Powertech   complete the project, after which the bank
        agreement (PPA) was signed in October   remained unanswered at press time. The   guarantee will be encashed proportionate to
        2017, with project completion time of 15   wind turbine generator has been going   the period. But it is clear that neither project
        months. But Leap Green Energy has yet to   through a difficult time. It had shuttered its   will be completed by June.