Page 187 - Facilities Master Plan 2016
P. 187
• New window treatments are needed
• The staff restrooms in the main office
need to be remodeled
• Office intercom is needed
• A new bell system is needed
• Wrought iron fencing at the front of the
school needs to be replaced
• Security cameras are needed at the rear
of campus
• The front office needs to be repainted
• The front landscaping needs to be
redone
• An electronic marquee is desired
• Pass keys for every door are desired
• A new trophy case is desired
• Additional shade is needed
• A stage is needed at the MPR
• HVAC needs to be replaced in Rooms
5,6, and 8
2515 Estate Drive, Stockton, CA 95209 Notes from Maintenance & Operations:
EXISTING SITE INFORMATION CONDITION ASSESSMENT • Replace all portable ramps/stairs
• Interior and exterior painting and flooring
Year Built: 1985 Recently Completed Work: • Common areas (restrooms, libraries,
Site Acreage: 11 acres etc.) need specialized access control
• N/A • More custodian storage
Student Population (2014-2015): 555 • Dumpster enclosures for 4 dumpsters
Grade Levels: K-6 • New emergency lighting battery backup
Notes/Comments from School Site: system
Total Number of Classrooms: 22 • Replace HVAC units at 15 portables
Number of Portables: 19 • Consolidate alarm pads in one central • Replace gas service line and 2 water
location heaters in kitchen
• Replace the laminate in all classrooms, offices • Portables may need siding repaired
and the library • Replace all locksets and closers
• Interior paint is needed in all classrooms • Recaulk windows
• All doors need to be painted • Re-roof 3 portables
5.24 EXISTING CONDITIONS ASSESSMENT Facilities Master Plan 188
CREEKSIDE ES Lodi Unified School District