SCOPE OF WORK CATEGORIES                                                                 COST



           1.  Modernize & Reconfigure Existing Classrooms                                    $  1,153,000

           2.  Existing Building Systems & Toilets                                            $  1,029,000

           3.  Site Utilities                                                                 $  2,451,000

           4.  Classrooms - New Construction                                                  $  6,949,000
           5.  Maker Spaces & Science Labs                                                    $  1,958,000

           6.  Electives                                                                      $     454,000

           7.  Performing Arts Improvements                                                   $     998,000
           8.  MPR/Food Service Improvements & Student Dining                                 $       60,000

           9.  Physical Education Improvements                                                           --

           10. Administration & Staff Support                                                 $  2,371,000

           11. Library & Student Support Services                                             $  1,115,000

           12. Safety, Security, & Campus Control                                             $  1,017,000
           13. District Support Facilities                                                               --

           14. Outdoor Learning Environment & Quads                                           $     184,000

           15. Exterior Play Spaces, Playfields, & Hardcourts                                 $  1,093,000
           16. Next Generation Classroom Flexibility (Furniture)                              $     195,000     The following items are
                                                                                                                excluded from this budget:
           17. Technology Infrastructure                                                                 --     •   Utility hook-up fees & City connection fees
                                                                                                                •   Off-site work and traffic signals
                                                                                                                •   Land acquisition costs
           Total Project Cost ($2016)                                                       $ 21,027,000        •   Hazardous material surveys
                                                                                                                •   Abatement and disposal
                                                                                                                •   Escalation (costs are in 2016$)

        5.34       COST SUMMARY ($2016)                                                                                        Facilities Master Plan  246