Page 272 - Facilities Master Plan 2016
P. 272
psychologist, counselor, etc.
• A new PA system is needed
• Exposed conduit needs to be addressed
• Visitor access at the perimeter of the All images taken by LPA.
campus needs to be addressed
• A larger MPR is needed
• A larger library is needed
• Kindergarten needs their own restrooms
and playground
• Classroom technology needs to be
updated
• A music classroom is needed
Notes from Maintenance & Operations:
• Replace all portable ramps/stairs
• Interior and exterior painting and flooring
• Common areas (restrooms, libraries,
etc.) need specialized access control
• More custodian storage
420 S. Pleasant Street, Lodi, CA 95240 • Dumpster enclosures for 4 dumpsters
• Upgrade EMS
EXISTING SITE INFORMATION CONDITION ASSESSMENT • Replace water heaters in custodian
closets
Year Built: 1938 Recently Completed Work: • Portables may need siding repaired
Site Acreage: 2.20 acres • Window sills need to be repaired
• Exterior paint • Replace 60% of door hardware
Student Population (2014-2015): 351 • Landscaping • Replace window sills
Grade Levels: K-6 • Some new carpet • Replace 50% of perimeter chainlink
• Student restrooms were upgraded for ADA fence
Total Number of Classrooms: 21 • Needs asphalt overlay at parking and
Number of Portables: 14 playgrounds
Notes/Comments from School Site: • Need new mop sinks
• Replace 6 trees
• Replace or repair old non-conforming • Needs irrigation automation, some
buildings so they can be used again piping replacement and new booster
• Additional administrative space is needed for pump
5.38 EXISTING CONDITIONS ASSESSMENT Facilities Master Plan 267
CLYDE W. NEEDHAM ES Lodi Unified School District