Page 463 - Facilities Master Plan 2016
P. 463

SCOPE OF WORK CATEGORIES                                                                 COST



           1.  Modernize & Reconfigure Existing Classrooms                                      $  818,000

           2.  Existing Building Systems & Toilets                                              $  435,000

           3.  Site Utilities                                                                   $  281,000

           4.  Classrooms - New Construction                                                             --
           5.  Maker Spaces & Science Labs                                                      $  234,000

           6.  Electives                                                                        $  390,000

           7.  Performing Arts Improvements                                                     $  241,000
           8.  MPR/Food Service Improvements & Student Dining                                   $  793,000

           9.  Physical Education Improvements                                                           --

           10. Administration & Staff Support                                                   $  479,000

           11. Library & Student Support Services                                               $  120,000

           12. Safety, Security, & Campus Control                                               $  496,000
           13. District Support Facilities                                                               --

           14. Outdoor Learning Environment & Quads                                            $     15,000

           15. Exterior Play Spaces, Playfields, & Hardcourts                                            --
           16. Next Generation Classroom Flexibility (Furniture)                               $   120,000      The following items are
                                                                                                                excluded from this budget:
           17. Technology Infrastructure                                                       $     32,000     •   Utility hook-up fees & City connection fees
                                                                                                                •   Off-site work and traffic signals
                                                                                                                •   Land acquisition costs
           Total Project Cost ($2016)                                                        $ 4,454,000        •   Hazardous material surveys
                                                                                                                •   Abatement and disposal
                                                                                                                •   Escalation (costs are in 2016$)

        5.62       COST SUMMARY ($2016)                                                                                        Facilities Master Plan  434