             Installation


             6-Nozzle Frame Assembly: Floor Mounted

              The following information is laid out installing the frames from exit end to entrance end. This could be
              different at your location due to tunnel configuration, equipment layout, etc.
              There are two head beam assemblies. One has the nozzles set at a 10° angle and the other is set
              straight up and down. The one with the 10° angle is to be installed on the entrance end frame.

                Exit End Frame Installation

                    1)  Locate the following parts:

                                       Item              Qty     Corner Clamp Pieces (2)
                           Dryer Leg Weldment             2

                           Corner Clamp Assembly          2

                           Black Plastic Caps             4
                           Lag Bolt 3 Zinc 5/8 x 6        8













                    2)  Locate the skid that the head beam assembly  shipped on. Clamp the head beam
                       assembly to the forks of the forklift and position it in its tunnel location.

                    3)  Lift it until there is a 91” clearance from the bottom surface of the head beam to the floor.


                    4)  Slide one of the clamp assemblies and one of the legs into place as shown below but do
                       not tighten the bolts until the height is set and the frame has been leveled. Be sure
                       the base of the legs face the entrance of the tunnel.

















                                                   Before                                  After