COSTO DE CAPITAL  TASA DE INFLACION  4,90%  0.0490  0.00408333    0.01225
                               PROYECTO A  PROYECTO B       PR=        INVERCION
              INVERCION INICIAL  $                              40,000.00  $   40,000.00  ANUALIDAD
            BENEFICIO TRIMESTRE 1  $                              13,000.00  $     7,000.00
            BENEFICIO TRIMESTRE 2  $                              13,000.00  $   10,000.00  PR MX =  BENEFICOS UTILIZADOS  (+)  FALTANTE A RECUPERAR
            BENEFICIO TRIMESTRE 3  $                              13,000.00  $   13,000.00  BENEFICIO PERIODO SIGUIENTE
            BENEFICIO TRIMESTRE 4  $                              13,000.00  $   16,000.00
            BENEFICIO TRIMESTRE 5  $                              13,000.00  $   19,000.00
                                       PERIODO DE RECUPERACION
                               PERIODO DE RECUPERACION PROYECTO A                           DIAS DEL AÑO
                  PR=      $                              40,000.00  3.07692308  9.23076923 9 MESES  30.41666667
                                             (=)
                           $                              13,000.00  0.23076923
                                                           7.01923077 7 DIAS
                                                           0.01923077
                                                           0.46153846
                                                           27.6923077 27 MINUTOS
               PERIODO DE RECUPERACION PROYTECTO B
           INVERCION INICIAL  $                              40,000.00
           BENEFICIO 1     $                                7,000.00
           FALTANTE A RECUPERAR  $                              33,000.00
           BENEFICO 2      $                              10,000.00
           FALTANTE A RECUPERAR  $                              23,000.00
           BENEFICO3       $                              13,000.00
           FALTANTE A RECUPERAR  $                              10,000.00

                        PR=              3   (+)  $   10,000.00  0.625   (=)       3.625             10.875 10 MESES
                                                  $   16,000.00                                       0.875
                                                                                                  26.61458333 26 DIAS
                                                                                                  0.614583333
                                                                                                      14.75 14 HORAS
                                                                                                      0.75
                                                                                                       45 45 MINUTOS
                    VALOR PRESENTE NETO
                       PROYECTO A
              INVERCION INICIAL  $                              40,000.00
            BENEFICIO TRIMESTRE 1  $                              13,000.00
            BENEFICIO TRIMESTRE 2  $                              13,000.00
            BENEFICIO TRIMESTRE 3  $                              13,000.00
            BENEFICIO TRIMESTRE 4  $                              13,000.00
            BENEFICIO TRIMESTRE 5  $                              13,000.00
              COSTO DE CAPITAL        1.225%
              VALOR PRESENTE        $62,677.89
             VALOR PRESENTE NETO    $22,677.89  SI SE ACEPTA EL PROYECTO
                       PROYECTO B
              INVERCION INICIAL  $                              40,000.00
            BENEFICIO TRIMESTRE 1  $                                7,000.00
            BENEFICIO TRIMESTRE 2  $                              10,000.00
            BENEFICIO TRIMESTRE 3  $                              13,000.00
            BENEFICIO TRIMESTRE 4  $                              16,000.00
            BENEFICIO TRIMESTRE 5  $                              19,000.00
              COSTO DE CAPITAL        1.225%
              VALOR PRESENTE        $62,325.70
             VALOR PRESENTE NETO    $22,325.70  SI SE ACEPTA EL PROYECTO