Roof sheathing.
CDX plywood sheathing, rough, power nailed, including normal waste.
1/2" B1@.013 SF 0.57 0.47 1.04
1/2", 4-ply B1@.013 SF 0.71 0.47 1.18
1/2", 5-ply B1@.013 SF 0.83 0.47 1.30
5/8", 4-ply B1@.013 SF 0.72 0.47 1.19
5/8", 5-ply B1@.013 SF 0.96 0.47 1.43
3/4" B1@.013 SF 0.85 0.47 1.32
Add for hip roof B1@.007 SF -- 0.26 0.26
Add for steep pitch or cut-up roof B1@.015 SF -- 0.55 0.55
Remove existing sheathing B1@.017 SF -- 0.62 0.62
OSB sheathing, rough, power nailed, including normal waste.
1/2" B1@.013 SF 0.68 0.47 1.15
5/8" B1@.013 SF 0.70 0.47 1.17
3/4" B1@.013 SF 0.77 0.47 1.24
7/8" B1@.014 SF 1.59 0.51 2.10
1-1/8" B1@.015 SF 2.29 0.55 2.84
Add for hip roof B1@.007 SF -- 0.26 0.26
Add for steep pitch or cut-up roof B1@.015 SF -- 0.55 0.55
Remove existing sheathing B1@.017 SF -- 0.62 0.62
Board sheathing, 1" x 6" or 1" x 8" utility T&G laid diagonal
1" utility T&G lumber, per MBF --@.000 MBF 1,939.20 -- 1,939.20
(1.13 BF per SF) B1@.026 SF 2.40 0.95 3.35
Add for hip roof B1@.007 SF -- 0.26 0.26
Add for steep pitch or cut-up roof B1@.015 SF -- 0.55 0.55
Remove board sheathing B1@.030 SF -- 1.09 1.09
Remove deteriorated boards B1@.034 SF -- 1.24 1.24
Remove boards in salvage condition B1@.036 SF -- 1.31 1.31
Remove and patch roof sheathing, rafters 24" on center, 3 in 12 pitch.
1" x 8" x 12' long, per board B1@.400 Ea 14.44 14.58 29.02
1" x 8", per square foot B1@.050 SF 1.80 1.82 3.62
1/2", 4-ply plywood, per 4' x 8' sheet B1@.960 Ea 17.07 34.99 52.06
1/2", 4-ply plywood, per square foot B1@.030 SF 0.55 1.09 1.64