TOTAL ELECTRIFIED RKM TKM
SC – DHNE SECTION 90.449 206.717
SC – MUE SECTION 52.337 98.063
III. Staff position [TrD] as on 30.09.2021
The total strength of Supervisory and Artisan staff involved in maintenance of
TRD assets (i.e, KCG/Depot) and manning of “Traction Power control” of
Hyderabad division is as under.
TKM Required staff Sanctions Act SHORTFALL
Sub-urban + As per yard stick (Sub- As on date
Non sub- urban 0.70, Non Sub-
urban urban 0.22)
155.732 41
+149.048 111 + 62 76 35
= 173
=304.748
a) Creation of 23 posts is pending Rly.board.
b) For creation of 51 posts in UR-MBNR sectionletter has been sent PCPO in
April 2021 after divisional approval and finance concurrence.
IV. Special Works carried out in HYB division:
a) RVNL Railway Electrification works
Staff were deputed at UR – GLY &GWD – RC sections for joint checking of TRD
b)
assets.
V. Punctuality cases- Failures:
SlNo Reason 2020-21(APR- MAY) 2021-22(APR-MAY)
1 Block burst - -
2 Insulator failures - -
3 Maintenance - -
4 Miscellaneous - -
5 Head on Collusion - -
Total - -
VI. Tower Car Position :
Tower car 8-Wheeler ICF make No. 4193 [DETC-190042] commissioned and
being utilised by KCG depot.