Page 94 - Best Practice for Construction Projects
P. 94

Bullet proofing live services




                •     Always risk assess the area for live
                      services before starting work.
                •     Any live services identified with the

                      potential of causing injury to you and/or
        11. Identification and Protection
                      damage/ impact to the service must be
                      protected.

                •     Level of protection to be agreed with
                      Jacobs / Client.

                •     Identify all services and protection of
                      services in the area on the SSoW/ Pre-
                      Task Assessment/SPA.

                •     Ensure agreed protection is in place before
                      starting. Remove when finished and make
                      good.

                •     Know the procedure to follow including
                      escalation to owner of the service in the
                      event of an impact. You may need LOTO
                      equipment, wet vac or other equipment at
                      the work location in case of an impact.

                •     STOP WORK – ASSESS – PROTECT
                      THE SERVICE!