Page 39 - PC Tax RFP
P. 39

 THE PERRY COMPANY
                                                                         39
ID
Task Name
Duration
Start Finish 2017 2018
55
56
58
57
59
60
Substantial Completion
10 days
2/9/18 2/23/18
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Final Inspections Develop Punchlist Certificate of Occupancy Punchlist Corrections
5 days 1 day 0 days 5 days 0 days
2/9/18 2/16/18
2/15/18 2/16/18
2/16/18 2/16/18 2/16 2/16/18 2/23/18
2/23/18 2/23/18 2/23
Final Completion
Project: Preliminary Schedule 4-13 Date: 4/14/17
Task Milestone
Summary Progress Critical
Hillsborough County Tax Collectors Office
South County Facility
The Perry Company