3.2 Create and review draft PI plans



































               Notes:


               Story Points

               As a Scrum Master, remind the team that when estimating stories to consider that a
               story point is a singular number that represent:

            ►  Volume: how much is there?
            ►  Complexity: how hard is it?
            ►  Knowledge: what do we know?
            ►  Uncertainty: what's not known?

               Compared with other Stories an 8-point Story should take relatively 4 times longer
               than a 2-point Story.

               PI Objectives:

               Objectives are business summaries of what each team intends to deliver in the upcoming
               PI. They often map directly to the Features in the backlog, but not always.

               Uncommitted Objectives:

               Uncommitted Objectives are used to identify work that can be variable within the scope
               of a PI. Stretch objectives are not the way for stakeholders to load the teams with more
               work than they can do. It’s not extra stuff to do, just in case time permits.