DATE 06/01/2020
SUBMITTED BY RA1811003020013 Ritesh Singh
RA1811003020034 Shubham Nandi
RA1811003020032 Yash Bha
TITLE / ROLE Nework Helper Using Kruskal's & Dijskstra's Algo
PROJECT PLANNING
Deadlines
S.no Task Date
1 Problem Statements Start Date - 24-12-2020
End Date - 31-12-2020
2 Stakeholders & Process Models Start Date - 31-12-2020
End Date - 07-01-2020
3 Identifying the Requirements from Problem Statements Start Date - 07-01-2020
End Date - 14-01-2020
4 Project Plan Start Date - 14-01-2020
End Date - 21-01-2020
5 Project Effort Based on Resources Start Date - 21-01-2020
End Date - 28-01-2020
6 Estimation of Project Metrics Start Date - 28-01-2020
End Date - 04-02-2020
7 Modeling UML Use Case Diagrams and Capturing Use Case Start Date - 04-02-2020
Scenarios End Date - 11-02-2020
8 E-R Modeling from the Problem Statements Start Date - 11-02-2020
End Date - 18-02-2020
9 Identifying Domain Classes from the Problem Statements Start Date - 18-02-2020
End Date - 25-03-2020
10 Statechart and Activity Modeling Start Date - 25-03-2020
End Date - 03-03-2020
11 Modeling UML Class Diagrams and Sequence diagrams Start Date - 03-03-2020
End Date - 10-03-2020
12 Modeling Data Flow Diagrams Start Date - 10-03-2020
End Date - 17-03-2020
13 Implementation Start Date - 17-03-2020
End Date - 24-03-2020
14 Estimation of Test Coverage Metrics and Structural Start Date - 24-03-2020
Complexity End Date - 30-03-2020
15 Designing Test Suites Start Date - 30-03-2020
End Date - 03-04-2020
16 Deployment Report Start Date - 03-04-2020
End Date - 10-04-2020