Page 35 - Gi flipbook February 2018
P. 35

offshore geological storage from a   kind (FOAK) projects is essential to   PROCESS OF CAPTURING
                 gas-fired power station, with the aim to   identify opportunities for efficiency   LEARNINGS
                 capture around one million tonnes of   enhancements, technology   For the PCCS project, the following
                 CO  per year, over a period of up to 15   development, and optimal project   process (Figure 5) was identified as
                    2
                 years, from an existing 400MW    team structures and ways of working.   best practice and utilised to capture
                 combined cycle gas turbine (CCGT)   These in turn can be applied to   lessons from the project:
                 located at SSE’s Peterhead power   follow-on projects across the industry   •  Define: The need for capturing
                 station in Aberdeenshire, Scotland. SSE   to realise cost reductions, and in turn   lessons learned was outlined, as well
                 was to be responsible for the flue gas   facilitate further deployment. This is   as the process to do so, the
                 emissions from which CO  was to be   the case for any new technology,   personnel to collate the lessons
                                    2
                 captured, electricity generation   including CCS, where although the   from, and production of specific
                 provision, and supporting services,   separate components of capture,   interview questions.
                 whilst Shell was to be responsible for   transport and storage have been   •  Collect: Capturing learnings was
                 CO  capture, compression, conditioning,   utilised across industry for many   undertaken ‘post-facto’ with project
                    2
                 transport and storage facilities.  years, the combined processes and   team members, including the project
                   The project completed front end   scale required for climate mitigation   Knowledge Transfer Manager, who
                 engineering design (FEED) work in   mean that costs for FOAK design,   was able to provide an integrated
                 2015, the same year in which the   construction and operation are higher   perspective whereby knowledge
                 project was cancelled due to UK   than for established technologies.   transfer was integrated into the
                 government withdrawal of funding for   Rubin et al., 2004  outlined this   project itself.
                                                                1
                 the UK CCS commercialisation     concept for technologies analogous to   •  Verify: All lessons captured were
                 competition. The project was in a   CCS, including flue gas        reviewed to ensure they were
                 position to progress to the next stage   desulphurisation (FGD) for power   relevant to CCS projects going
                 of the development process, and,   plant emissions control, where capital   forward, and also to identify if they
                 from a technical standpoint,     costs for FGD technology experienced   could be utilised for non-CCS capital
                 construction and operation was   declines over time as cumulative   engineering projects.
                 deemed feasible. In terms of     capacity increased (Figure 4). The   •  Store: The lessons captured were
                 constructability and tendering, the   lower costs realised were attributed   collated in a database and made
                 project drew competitive bids,   primarily to technology innovation, as   available to staff for future use.
                 reflecting the comprehensive FEED   well as process improvements, and   •  Disseminate: Opportunities taken to
                 work undertaken, and the evident   subsequent increased competition   disseminate lessons captured.
                 technical viability of the project.   among vendors as deployment
                 Following the project cancellation, the  capacity increased.
                 need to capture lessons from both
                 the FEED work and the project
                 development in general became
                 imperative, due to the impending   FIGURE 2. A) Low carbon power production from natural gas with CCS; B) Low carbon
                 demobilisation of the project team.  hydrogen production from steam methane reforming/auto thermal reforming, with CCS.
                                             2
                   The PCCS project comprised CO
                 capture from flue gas produced by
                 one of the gas turbines at Peterhead
                 Power Station, using amine-based
                 technology provided by Shell Cansolv
                 (a wholly-owned subsidiary of Shell).
                                  2
                 After capture, the CO  would have
                 been compressed, cooled and
                 conditioned to meet transportation
                 and storage specifications. The
                 resulting dense-phase CO  stream
                                     2
                 would be transported via a new   FIGURE 3. Peterhead carbon capture and   FIGURE 4. Capital cost of a new wet
                 pipeline which would tie-in to an   storage project location      limestone FGD system for a standardised
                 existing offshore pipeline, transporting                          coal-fired power plant (500MWe, 3.5 per
                       2
                 the CO  more than 100km off the                                   cent sulphur coal, 90 per cent SO2 removal)
                 east coast of Scotland before tie-in                              as a function of cumulative worldwide
                 subsea to the existing Goldeneye                                  capacity of FGD installations, showing
                 platform (Figure 3). Once at the                                  decrease in capital cost as a function of
                 platform, the CO  would be injected                               global capacity, analogous to CCS
                               2
                 more than 2km under the sea bed of
                 the North Sea into the depleted
                 Goldeneye gas reservoir for
                 permanent geological storage.

                 IMPORTANCE TO INDUSTRY OF
                 CAPTURING LEARNINGS
                 Capturing learnings from first-of-a-



                                                                                                               35


        IGEMNews_YPPC.indd   2                                                                                    18/01/2018   15:44
   30   31   32   33   34   35   36   37   38   39   40