Page 2 - The Inside Track - April 2019
P. 2

Volume 3 | Issue 2 | April 4, 2019
    Railroad Construction Company, Inc. / Beach Electric Company / RCC Fabricators , Inc. / Power Design & Installation Group / RCC Builders & Developers, Inc.
        (continued from page 1)  the railroads, but also makes for  with rail weighing upwards of   Consistent performance has
                                 vital safety awareness amongst  136 pounds.                 allowed RCC’s Track Department
   10,  2019  at  a  contract  value  of   crews. Harold Trackwork Part 3                    to not only continue working
   $23  million.  While  the  contract   and the other ESA contracts that   Turtle Back Zoo features over   through nearly a century of
   amount may seem substantial   RCC has completed are some of   1,400 animals including wolves,   economic ups and downs,
   as a single project, it is only   the most complex, dangerous,   giraffes, kangaroos and dozens of   but  to thrive. Projects  ranging
   0.2% of the projected total ESA   and exciting that the company   other  species  one would never   from a few thousand dollars
   Contract value. The project   has performed. Nonetheless,   find in the wilderness of New   to multi-million have allowed
   included work in three different   massive junctions are not the   Jersey. The railroad attraction   the  Department  to  expand  its
   areas: the Northeast Quadrant,   only  places  where  trackwork  is   that runs from the site goes   horizons while grounding itself
   the Southeast Quadrant, and the   needed.                   throughout  South  Mountain   in the roots of the company.
   Westbound Bypass.                                           Reservation, a 2,000+-acre nature
                                   RCC    was   contracted  to  reserve that borders the zoo very   As RCC continues to grow, the
     The purpose of the project                                                              Track Department grows with it.
   was to remove and replace ten   perform trackwork at the famous  different to the urban Queens
                                 Turtle Back Zoo in late 2018. For  location of Harold Interlocking.
   turnouts, as well as 6,800 feet of   years, Turtle Back’s “Zoo Train”
   track and concrete ties weighing   has taken visitors on a relaxing
   over 800 pounds each. A rail   ride through the 20-acre site.
   turnout, or “switch,” is a portion   However,  when construction
   of track where the rail splits in   of a new parking deck began in
   two directions, enabling trains   2018, the ride’s track needed  to
   to  be  guided  from  one  track  to   be rerouted. That’s where RCC’s
   another. Turnouts are arguably   Track Department came in.
   the most defining characteristic
   of a rail junction, and Harold   The old track was modified and
   Interlocking, as the busiest  relocated to accommodate a new
   junction in the country, has  “train house.” Differing from the   ABOVE: The 2016 Ben Franklin Bridge Project replaced an entire track system including 2.5 miles
                                                               of rail. The project required a 60-day outage for each individual track. In his 16 years at RCC, Jeff
   many.                         mass of the ESA project, Turtle   McKeon described this project as the most exciting of his career.
                                                               BELOW: RCC co-workers construct new rail at Harold Interlocking in Queens.
                                 Back  Zoo’s  new  track  required
     Over 40 trains pass through
   the interlocking per hour, totaling   only 15-foot turnouts with rail
                                 weighing  only  20  pounds.  In
   nearly 800 per week. Not only   contrast, the turnouts at Harold
   does this make for frustrating   Interlocking were 260 feet long
   coordination between RCC and
          Field Photo of the Month




                                                                    (continued from page 1)  bracing.”
                                                                Two fracture-critical, galvanized,
                                                                cantilevered sign structures with   Both new contracts will
                                                                walkways are to be created for   allow RCCF to utilize two new
                                                                the Connecticut DOT.         pieces of equipment. As of late
                                                                                             February 2019, RCCF has been
                                                                  A   second   new    client,  using a new beamline machine,
                                                                Schiavone Construction, has   the  aforementioned  Ocean
                                                                been  added  to  RCCF’s  roladex.   Avenger, which enables drilling,
                                                                RCCF has been contracted     sawing,  punching, shearing,
                                                                to  fabricate  and   deliver  coping or fabrication of almost
                                                                approximately  2-million  pounds   all  types  of structural  steel
                                                                of  repair  and  new  steel  for  the   profiles.
                                                                upgrades of several structures
                                                                along the NJ Turnpike.         Further,  RCCF    acquired
                                                                                             a new Angle Line (pictured
                                                                  “We  will  put  all  three  of our   below), the aforementioned
    Project:      Flood Mitigation - Resiliency at 17 Fan Plants   pieces of equipment to use on   Ocean Clipper, in early March
                                                                this one,” said RCCF President   which allows the company to
    Owner:        New York City Transit Authority               and co-worker Scott Vesper   punch or shear angles for most
                                                                about the Schiavone contract,   any job.
    Photographer:   Rich France                                 “Our plasma table for the cutting
                  Senior Project Manager                                                       As RCCF’s work-on-hand
                                                                of parts, our Ocean Avenger for
    Date Taken:   March 21, 2019                                the drilling of beams and plates   continues  to  climb,  the
                                                                                             company is ensuring that it has
                                                                and our Ocean Clipper for the
    About:        Placing concrete via a pump truck for flood walls    fabrication  of  angle  clips  and   the resources to meet clients’
                  inside vent building located at FDR & 63rd Street                          demands.
   1   2