Earthwork support

               D.13  Generally

                     Sheet piling, contiguous piling, secant piling, ground anchors, diaphragm wall, soldier piling,
                     close timber piling and guniting shall each be given separately in accordance with the various
                     Sections.

               D.14 Definitions

                     Earthwork support shall be deemed to mean providing everything requisite to uphold the side of
                     excavation by whatever means necessary (other than interlocking driven sheet steel piling) and
                     shall be deemed to be inciuded with the various items of excavation. (Earthwork  support
                     includes the use of timber planking and strutting, plywood trench sheeting, light steel trench
                     sheeting and strutting). Interlocking driven sheet steel piling is not covered by the terms
                     "Earthwork support” and where this is required by the design  or specification not at the
                     Contractor's choice, it should be measured in accordance with Section E.

                     Disposal of water

               D.15  Surface water

                     An item shall be given for keeping the surface of the site and the excavations free of surface
                     water.

               D.16  Water in the ground

                     Where excavation is measured below the water level in accordance with clause D.12.14, an
                     item shall be given for keeping the excavations free of ground water.

                     Disposal of excavated material

               D.17  Multiple handling

                     Multiple handling  of excavated materials and transporting about the site shall be deemed to be
                     included with the items of final disposal. Multiple handling which is specifically required shall be
                     given in the description of disposal items.

               D.18  Disposal on site

                     Excavated materials to be deposited on site in permanent spoil heaps or spread on site shall
                     each be given in cubic metres stating any requirements for the location of such deposits or the
                     average distance from the excavation in metres or kilometres.

               D.19 Disposal off site

                     Excavated materiais to be removed from the site shall be given in cubic metres and so
                     described and the provision of a shoot, dump or tip including payment for royalties, fees, levies
                     and other charges shall be deemed to be included with the items unless otherwise stated.

               D.20 Topsoil spread on site

                     Preserved and imported topsoil spread on site shall be so described and given in accordance
                     with ciause D.26.