Page 24 - PR 2014 2016 09 Nuclear Reactors and Fuel Cycle
P. 24
268 Nuclear Reactors and Fuel Cycle | Progress Report
BEFORE
AFTER
Figure 31. Stainless steel pipe of the Reactor Primary Cooling Circuit (before and after partial substitution)
2016 Instrumenta- Acquisition of 3 new chambers (fis- Concluded.
tion and Con- sion, compensated ionization and
trol System non-compensated ionization) to be
used as instrumentation of the elec-
tronic circuit for monitoring the
power and safety of the reactor.
2016 Monitoring IPEN Meteorological Tower for data Reformed and
system acquisition for studies of radioac- repositioned, in
tive dissipation in case of accidents conjunction with
with release of fission products. the CEN / IPEN
technical team.
2016 Communica- Telephone facilities of the Reform concluded.
tion System reactor building.
2016 Electric Acquisition of a new Moto Gen- Waiting for in-
System erator of 220 Volts and power of stallation.
230 kVA, to replace an equipment
that has been operating since
1974, whose maintenance is dif-
ficult due to lack of spare part.