Gasparilla Inn - Gulf Cottages
                                                     Concept Budget Estimate 10-19-17
                                                                                         Unit
              Code                       Description                    Quantity  Unit   Cost      Amount      Total Cost
                                                                                             TOTAL AMOUNT =>            1,488,934
                    Gulf Cottages Square Footage  3,591 acsf

             Div 2  Site Survey & Layout                                                                                      2,500
                      Site Survey & Layout - Lsum                                          1   ls              2,000.00                2,000
                      Misc Survey work                                                     1   ls                 500.00                   500
             Div 2  Clearing & Earthwork                                                                                      2,500
                      Clearing & Earthwork - Lsum                                          1   ls                     -                     -
                      Earthwork & Grading (Based upon "Pad Ready" Site)                       1  ls  Included w above
                      Rough & Finish Grading                                               1   ls              2,500.00                2,500
             Div 2  Piling                                                                                                  67,445
                      Piling - Lsum                                                        1   ls                     -                     -
                      12" Diameter Auger Cast Piling                                47.00   ea             1,310.00               61,570
                      Piling Cut-offs, Drill & Dowel                                47.00   ea  Included w above
                      Pile Monitoring & Testing                                     47.00   ea                  50.00                 2,350
                      Pile Layout, Staking & Asbuilts                               47.00   ea                  75.00                 3,525
             Div 2  Site Utilities                                                                            w/ Site Cost
                      Site Utilities - Lsum                                                1   ls                     -                     -
             Div 2  Soil Treatment                                                                                               465
                      Soil Treatment - Lsum                                                1   ls                     -                     -
                      Soil Treatment                                                3,100   sf                    0.15                    465
             Div 2  Landscaping, Sod & Irrigation Allowance                                                   w/ Site Dev
                      Landscaping, Sod & Irrigation - Allowance                            1   ls                     -   w/ Site Dev
                      Landscape Trees, Plantings & Mulch                                   1   ls  Included w above
                      Bahia Sodding                                                        1   ls  Included w above
                      Irigation System                                                     1   ls  Included w above

             Div 2  Concrete Pavers                                                                                         11,250
                      Concrete Pavers - Lsum                                               1   ls                     -                     -
                      Concrete Pavers - Sand Set (Under Building)                   1,325   sf                    6.00                 7,950
                      Crushed Shell with weed barrier                               1,200   sf                    2.75                 3,300
             Div 3 & 4  Concrete & Masonry                                                                                225,331
                      Concrete & Masonry - Lsum                                            1   ls          225,331.00            225,331
                      Conc Grade Beam Foundations - GB1 & GB2                            63   cy  Included w above
                      Pile Cap - 2 PC                                                      3   ea  Included w above
                      Pile Cap - 3 PC                                                      1   ea  Included w above
                      Pile Cap - 5 PC                                                      1   ea  Included w above
                      Slab on Grade - Frangible                                        290   sf  Included w above
                      Second Floor 2" Topping Slab                                  3,035   sf  Included w above
                      Second Floor 2" to 3-1/2" Topping Slab                           284   sf  Included w above
                      Conc Columns C1                                                      1   ea  Included w above
                      Conc Columns C2                                                    26   ea  Included w above
                      Conc Columns C3                                                      2   ea  Included w above
                      Conc Columns C5                                                      2   ea  Included w above
                      Conc Columns C6                                                      1   ea  Included w above
                      Conc Columns C7                                                      1   ea  Included w above
                      Conc Columns C8                                                      1   ea  Included w above
                      Conc Columns C9                                                      1   ea  Included w above
                      Conc Columns C10                                                     1   ea  Included w above
                      Conc Beams B1                                                    271   lf  Included w above
                      Conc Beams B2                                                      70   lf  Included w above
                      Conc Beams B3                                                      21   lf  Included w above
                      Conc Beams B4                                                      21   lf  Included w above
                      Conc Beams B5                                                      34   lf  Included w above
                      Conc Beams B6                                                      32   lf  Included w above
                      Tie Beams                                                        270   lf  Included w above
                      Raked Tie Beams                                                  142   lf  Included w above
                      8" CMU Walls                                                     479   lf  Included w above
                      8" Concrete Walls                                                  32   lf  Included w above
                      14" Concrete Walls                                                 20   lf  Included w above

             Div 3  Structural Precast Planks                                                                               30,942
                      Structural Precast - Lsum                                            1   ls                     -                     -
                      6" Hollow Core Plank                                             560   sf                    8.50                 4,760
                      8" Hollow Core Plank                                          2,756   sf                    9.50               26,182