Page 300 - 2018 DIGITAL BROCHURE
P. 300

Hurst Brook



       The Hurst Brook which carries water from the Pennine hills passes through Glossop town centre.

       During the construction of the Town Hall, in the 18th Century, it was decided to Culvert a length of the river to
       extend the market place and provide a space for parking. The Culvert was constructed using masonry sidewalls
       with a brick arch crown section. The structure was then backfilled.

       Subsequent to this a sewage pipe was placed in the river channel with manhole connections in two places along
       the culvert length. During a recent storm one of these manholes, in the centre of the culvert, became dislodged
       bringing with it a section of the masonry sidewall. This instability lead to an area of the car park being fenced off
       and a requirement for a repair to the culvert lining.


            Pollution of the watercourse
            Problems with access
            Lack of details of the existing structure
            Changes to the river flow
            Risk of further collapse

       High Peak Council asked Derby City Council Water Management Engineers to prepare a scheme for the reme-
       dial works. The final solution was a team effort involving input from the following parties:
            Whitehouse Construction, as Facility
              Managers and Main Contractor Special-
              ist Engineering Services Contracting
              Division, as specialist Sub-Contractor
            Natural Cement Distribution, as spe-
              cialist material supplier.



            The use of natural material avoiding the
              use of potentially harmful construction
              chemicals
            The use of bagged materials, which
              could be easily stored on site and
              transported to the job site


       The key features included:

       A brief description of the method was as follows. SES formed a project team involving John Shone as Project Engi-
       neer and Colin Cook as Site Manager. Access was made to the culvert by forming a ramp at the downstream end.
       Bunds were also formed in the river channels.A temporary island was formed adjacent to the damaged section
       using stone filled IBC bags. The dry shotcrete machine was placed onto this island and bagged NATCEM 430F
       transported to the site in dump trucks. The blockwork was removed from the top working downwards. As each
       section was removed the area was secured with a layer of NATCEM 430F. This material contains Bekaert Dramix
       30.5 steel fibres at the rate of 30kgs per cubic metre.

       This provided initial primary support to the lining above and prevented any unravelling of the loose fill behind.
       On completion the secondary lining was sprayed back to the original tunnel profile.
       The work was safely completed and the car park fully re-opened ready for the Christmas Market.
   295   296   297   298   299   300   301   302   303   304   305