Page 53 - Phelan Energy Green Ammonia Plant Egypt
P. 53
Project Timelines (Pilot Phase)
Process with government
Offtake and land transfer Selection of equity partners Lender process
FC and Construction Start Construction
2022
Q2 Q3 Q4
2023
Q1 Q2 Q3 Q4
2024
Q1 Q2 Q3 Q4
2025
Q1 Q2 Q3 Q4
2026
Q1 Q2
Proposal to government
MoU with government
Definitive Agreement signing - COP 27
Offtake agreement/s finalization
Land transfer process
SHA signing
JDA with equity investors
Finance plan preparation
Lender selection
Term sheet agreement with lenders
Lenders DD process
`
Execution of financing agreements
FC and Construction Start
Pre-feasibility
Engg. Design
Material Procurement/Equipment Supply
Erection
Commissioning
© Phelan Energy Group 53