Page 53 - Phelan Energy Green Ammonia Plant Egypt
P. 53

  Project Timelines (Pilot Phase)
Process with government
Offtake and land transfer Selection of equity partners Lender process
FC and Construction Start Construction
                   2022
Q2 Q3 Q4
2023
Q1 Q2 Q3 Q4
2024
Q1 Q2 Q3 Q4
2025
Q1 Q2 Q3 Q4
2026
Q1 Q2
   Proposal to government
 MoU with government
 Definitive Agreement signing - COP 27
 Offtake agreement/s finalization
 Land transfer process
 SHA signing
 JDA with equity investors
 Finance plan preparation
 Lender selection
 Term sheet agreement with lenders
 Lenders DD process
`
 Execution of financing agreements
 FC and Construction Start
 Pre-feasibility
 Engg. Design
 Material Procurement/Equipment Supply
 Erection
 Commissioning
           © Phelan Energy Group 53
 