Project Client Scope of works
PRE AND POST CONSTRUCTION BUILDING CONDITION SURVEY
4-lane road tunnel – cut and
Sheikh Zayed Street cover, 3 km long; 4 Samsung – Saif Bin Pre/Post survey of 186 structures,
tunnel project, Abu interchange underpasses, Darwish Joint upto 54 storeys
Dhabi Venture/Parsons
each 1 km long.
16 km long sewerage
Muharraq STP Project, tunnel, micro-tunneling Samsung Engineering Pre/Post survey of almost 390
Bahrain Co. Ltd. structures
project
Contract T01: 13 km main Samsung C&T Pre/Post survey
sewer deep gravity tunnel Corporation, Korea
Contract T02 & T03: 25.5 km
main sewer deep gravity Impregilo, Italy Pre/Post survey
Strategic Tunnel tunnel
Enhancement Contracts LS01 & LS02: 42 km
Programme (STEP) link sewer deep gravity Zublin, Germany Pre/Post survey
Project, Abu Dhabi
tunnels
Contract PS01: 100 m deep
x 55 m dia underground Odebrecht, Brazil Post construction survey
Pump Station
Dubai Water Canal Canal and Coastal Works Belhasa Six Construct
Infrastructure (R999/3) L.L.C (Besix)/RTA Pre/Post survey
Package-3
Gold Line
13.5 km tunnel with 10 ALYSJ JV Pre/Post survey
stations
Gold Line Underground ALYSJ JV Pre/Post survey
Extension Design Stage ~790 structures and 3700 utilities
Green Line
Doha Metro Project ~16.6 km tunnel with 8 PSH JV Pre/Post survey and Structural
survey ~ 185 structures
stations
Major stations SOQ JV Pre/Post survey
(underground)
Red Line South QGD JV Pre/Post survey
~12 km tunnel with 8 stations ~585 structures
Enabling works HSP Enabling JV Pre survey
Expolink Route 2020 Dubai Metro extension Expolink-CWJV Pre-construction survey
Inner Doha ~30 km Main Trunk Sewer
Resewerage tunnel BYTP - UCC - BCQ - Pre/Post survey
Implementation Contracts MTS-01~16 km; BESSAC JV structure/building/utility
Strategy (IDRIS) MTS-03~14 km
Inner Doha Al Sraiya Strabag -
Resewerage ~15 km Main Trunk Sewer Hochtief - Petroserv Pre/Post survey
Implementation tunnel - Contract MTS-02 JV structure/building/utility
Strategy (IDRIS)
AI Quid Towers, Doha Foundation works Ammico Contracting Pre construction survey
Delhi Metro Project Packages CC01, CC04, Various Contractors Pre/Post survey
Phase III Started 2011 CC05
Package UGC-01 L&T-STEC JV
Mumbai Metro Package UGC-02 HCC-MMS JV Pre-construction survey
Package UGC-03 Dugus-Soma JV
Package UGC-04 CEC-ITD-TPL JV
Mumbai Metro Pre-construction survey
Package UGC-07 L&T-STEC JV
www.encardio-moniterra.com Over 50 years of excellence through ingenuity 23