Project                       Client              Scope of works
           PRE AND POST CONSTRUCTION BUILDING CONDITION SURVEY
                                  4-lane road tunnel – cut and
           Sheikh Zayed Street    cover,   3   km   long;   4   Samsung – Saif Bin   Pre/Post survey of 186 structures,
           tunnel project, Abu    interchange   underpasses,   Darwish Joint      upto 54 storeys
           Dhabi                                             Venture/Parsons
                                  each 1 km long.
                                  16 km long sewerage
           Muharraq STP Project,   tunnel, micro-tunneling   Samsung Engineering   Pre/Post survey of almost 390
           Bahrain                                           Co. Ltd.             structures
                                  project
                                  Contract T01: 13 km main   Samsung C&T          Pre/Post survey
                                  sewer deep gravity tunnel     Corporation, Korea
                                  Contract T02 & T03: 25.5 km
                                  main sewer deep gravity    Impregilo, Italy     Pre/Post survey
           Strategic Tunnel       tunnel
           Enhancement            Contracts LS01 & LS02: 42 km
           Programme    (STEP)    link sewer deep gravity    Zublin, Germany      Pre/Post survey
           Project, Abu Dhabi
                                  tunnels
                                  Contract PS01: 100 m deep
                                  x 55 m dia underground     Odebrecht, Brazil    Post construction survey
                                  Pump Station
           Dubai Water Canal      Canal and Coastal Works    Belhasa Six Construct
           Infrastructure         (R999/3)                   L.L.C (Besix)/RTA    Pre/Post survey
           Package-3
                                  Gold Line
                                  13.5 km tunnel with 10     ALYSJ JV             Pre/Post survey
                                  stations
                                  Gold Line Underground      ALYSJ JV             Pre/Post survey
                                  Extension Design Stage                          ~790 structures and 3700 utilities
                                  Green Line
           Doha Metro Project     ~16.6 km tunnel with 8     PSH JV               Pre/Post survey and Structural
                                                                                  survey ~ 185 structures
                                  stations
                                  Major stations             SOQ JV               Pre/Post survey
                                  (underground)
                                  Red Line South             QGD JV               Pre/Post survey
                                  ~12 km tunnel with 8 stations                   ~585 structures
                                  Enabling works             HSP Enabling JV      Pre survey
           Expolink Route 2020    Dubai Metro extension      Expolink-CWJV        Pre-construction survey
           Inner Doha             ~30 km Main Trunk Sewer
           Resewerage             tunnel                     BYTP - UCC - BCQ -   Pre/Post survey
           Implementation         Contracts MTS-01~16 km;    BESSAC JV            structure/building/utility
           Strategy (IDRIS)       MTS-03~14 km
           Inner Doha                                        Al Sraiya Strabag -
           Resewerage             ~15 km Main Trunk Sewer    Hochtief - Petroserv   Pre/Post survey
           Implementation         tunnel - Contract MTS-02   JV                   structure/building/utility
           Strategy (IDRIS)
           AI Quid Towers, Doha     Foundation works         Ammico Contracting    Pre construction survey
           Delhi Metro Project    Packages CC01, CC04,       Various Contractors   Pre/Post survey
           Phase III Started 2011   CC05
                                  Package UGC-01             L&T-STEC JV
           Mumbai Metro           Package UGC-02             HCC-MMS JV           Pre-construction survey
                                  Package UGC-03             Dugus-Soma JV
                                  Package UGC-04             CEC-ITD-TPL JV
           Mumbai Metro                                                           Pre-construction survey
                                  Package UGC-07             L&T-STEC JV


         www.encardio-moniterra.com                    Over 50 years of excellence through ingenuity           23