Cost Breakdown                                                            Funding Sources

        Men’s Locker Room & Fitness Renovations ........................................ $4,400,000  1.  Special Assessment ................................................................$10,040,000

        Indoor Tennis Mezzanine Renovations .................................................. $200,000  2.  Entrance Fee Increase ..............................................................$1,123,873
        Squash Court Conversion ................................................................... $1,800,000  3.  Cash Flow from Operations ......................................................$4,236,127
        Paddle Tennis Complex .......................................................................... $700,000  TOTAL FUNDS RAISED ...................................................... $15,400,000
        Four Hard Surface Tennis Courts ........................................................... $700,000
        Surface Parking Solution ..................................................................... $1,300,000  Key Funding Information
        Pool Complex ...................................................................................... $3,700,000
                                                                                   1.  Significant assessment discounts provided to senior members
        Grounds/Maintenance Facility ........................................................... $1,400,000
        Social Garden ........................................................................................ $500,000  2.  Non-Residents and young members (under age 28) not assessed
                                                                                   3.  Financial modeling based on separate memberships for both fitness and
        Main Clubhouse Elevator ...................................................................... $600,000  the pool
        Temporary Locker Room Facility Lease .................................................. $100,000  4.  Minimizes dues increases over the term of the assessment
        TOTAL COST ................................................................................ $15,400,000  5.  Marginally increases future entrance fees to partially fund the project
                                                                                   6.  Minimizes the use of long-term debt
        The above expected costs are total project budgets including demolition,
        construction costs, landscaping, furnishings, fixtures, equipment, professional
        fees, contingencies and assumed escalation. These figures are used to
        represent reasonable construction budgets based on early conceptual designs
        and would have to be verified based on further design and engineering. The
        following assumptions were made in developing the budgets:

            •  20% project contingency
            •  Additional 5% project contingency that covers the Men’s Locker Room
              Building renovations
            •  4% per year escalation assumption