Page 95 - INTEGRADORA II IDIE 10° Sebastian Valentin Gamez Hernandez
P. 95
ACTIVIDADES UTP
Project Management CPM
Data
Time
A 1
B 2 A
C 2 A B
D 2 A B C
E 3 B C D
F 3 B E
G 3 F
H 4 F G
I 2 F G H
Results
Task Early Start Early Finish Late Start Late Finish Slack
A 0 1 0 1 0
B 1 3 1 3 0
C 3 5 3 5 0
D 5 7 5 7 0
E 7 10 7 10 0
F 10 13 10 13 0
G 13 16 13 16 0
H 16 20 16 20 0
I 20 22 20 22 0
Project 22
Early start computations
A 0 0 0 0 0 0
B 1 0 0 0 0 0
C 1 3 0 0 0 0
D 1 3 5 0 0 0
E 3 5 7 0 0 0
F 3 10 0 0 0 0
G 13 0 0 0 0 0
H 13 16 0 0 0 0