Page 8 - Barr&Barr_HealthcarePortfolio.indd
P. 8

Trinitas Hospital

                                                4th Floor Oncology Care Center


































          SIZE                     OWNER
          14,000 square feet       Trinitas Regional
                                   Medical Center
          CONTRACT TYPE
          Construction Manager-at-Risk  ARCHITECT
                                   Pallante Design






                                                                       PROJECT DETAILS

         Originally constructed in 1964 as a med/surg unit the time had arrived       •   Th  e project required the total gut demolition of
         to convert the fl oor for cancer care.                            the space while at the same time not disturbing
                                                                           the services of the renal dialysis and endoscopy
                                                                           centers on the fl oor immediately below.
                                                                          •   Detailed phasing scenarios incorporating “after
                                                                           hours” shift work  accommodated the installation
                                                                           of the new mechanical, electrical and plumbing
                                                                           systems.
                                                                          •   High end fi nishes throughout the project have
                                                                           created a warm, caring environment for the
                                                                           patients.
   3   4   5   6   7   8   9   10   11   12   13