Build
                                           Places stakes at the                         Tie a string from       Use the soil excavated from the uphill   2  37
                                           uphill and downhill                          the ground level of     side to fill the downhill area up so
                                           sides and about 5 feet                       the uphill stake to     that the area is flat. Very lightly tamp
                                           apart along the length                       the downhill stake      down the soil by walking over the fill
                                           of your rain garden.                         so that it's level.     after every few inches are added.

                                                           Leveling String



                                                                                            SLOPE
                                                                         Original Surface
                                                                                                                                           BERM

                  Cross Section View                                  Soil Removed to Fill Berm
                  of Method 2






                                                                                                 Create a berm at the downhill side to confine water in the rain
                                                                                                 garden. For the correct height, build the berm up to the string.
            Excavating On Slopes


            If the rain garden area is sloped more than 5%, then consider one of the following
            two methods for excavating soil to the necessary depth.

            Method 1: Dig the downhill side to the desired depth and create a flat bottom.
            This means that the depth at the uphill side will be more than the downhill
            side, which is good for additional water storage but requires more digging.
            Set the soil aside for reuse and/or disposal.

            Method 2: An alternative method (shown on this page) to get the desired depth             Stakes
            on slopes is to excavate soil from the uphill end and use the soil to fill and
            create a berm to get the desired depth at the downhill end. If you choose this
            method, do the following:


            •  Place stakes at the uphill and downhill sides and about 5 feet apart along             Plan View of
               the length of the rain garden.                                                         Method 2
            •  Tie a string from the ground level of the uphill stake to the downhill stake so                                           BERM
               that it’s level. A small, lightweight line level works well for this.
            •  Rather than tie all strings to the stakes at once, work with one at a time and
               in 5-foot sections so that the strings don’t get in your way.
   38   39   40   41   42   43   44   45   46   47   48