Project Schedule



                                                            Ecommerce Portal Development












        Phases/ Duration              01                      02 -05                          06                    07             08

        in weeks

        Purchase Order, Software                  Design Stage                      Migrating         Data System              UAT      &
        Signing                Requirement        (Theme Setup & Design from                  Old      Side Testing       & Project

        Software               Analysis           Customization + Setting Using                  Magento Deployment Closure
        Development                               Extensions )                      Connect                                    (GO
        Agreement         &                                                                                                    LIVE)

        Lead Time



















    Givioftient – WhiteBoardsnz.com
    Cl
   10   11   12   13   14   15   16   17   18   19   20