Page 212 - Vessel Sanitation Program 2018 Operations Manual
P. 212

VSP 2018 Operations Manual



                       12.13.2 Documentation

                          12.13.2.1 Detailed Justification
                                     Before a VARIANCE from a requirement of the VSP 2018 Operations
                                     Manual is APPROVED, the person requesting the VARIANCE must
                                     provide the following, which will be retained in VSP’s file on the vessel or
                                     vessels:


                                         •  A statement of the proposed VARIANCE from the VSP 2018
                                            Operations Manual requirement including relevant section number
                                            citations.


                                         •  An analysis of the rationale for how the potential public health
                                            HAZARDS and nuisances addressed by the relevant VSP 2018
                                            Operations Manual requirement will be alternatively addressed by
                                            the proposed VARIANCE.


                                         •  If required, a HACCP PLAN, standard operating procedures,
                                            training plan, and monitoring plan that includes all the information
                                            as it is relevant to the VARIANCE requested.


                                         •  Additional scientific data or other information as required to
                                            support the determination that public health will not be
                                            compromised by the proposal.

                       12.13.3 Conformance


                          12.13.3.1 Conformance
                                     If VSP grants a VARIANCE, the vessel must

                                     •   Comply with the HACCP PLANS, standard operating procedures,
                                         training plan, and monitoring plan submitted and APPROVED as a
                                         basis for the modification or waiver.

                                     •   Maintain and provide to VSP, on request, records to demonstrate that
                                            o procedures monitoring CRITICAL CONTROL POINTS are
                                                effective,
                                            o monitoring of the CRITICAL CONTROL POINT are routinely
                                                used,
                                            o necessary corrective actions are taken if there is failure at a
                                                CRITICAL CONTROL POINT, and
                                            o effectiveness of the operation or process in protection of public
                                                health is periodically verified.








                                         Section 12: Administrative Guidelines; 183