Productivity Norms of Scaffolding
SL ASSESSMENT DESCRIPTION PRODUCTIVITY
NO
1 F1a Erection and Dismantle HD 0.20 M.Hrs/Cum
Rectangular tower
2 F1b Erection and Dismantle HD 0.30 M.Hrs/Cum
Square tower
3 F2 Erection and Dismantle L&T 0.40 M.Hrs/Cum
System Stair Tower
4 F3 Erection and Dismantle LD 0.10 M.Hrs/Cum
or Access Scaffold Tower
5 F4 Erection and Dismantle Pipe 0.50 M.Hrs/Cum
& Cup lock Scaffolding
6 F5 Erection and Dismantle Cup 0.50 M.Hrs/Cum
lock Scaffolding