Productivity Norms of Scaffolding




            SL  ASSESSMENT                           DESCRIPTION                       PRODUCTIVITY


            NO

             1             F1a            Erection  and Dismantle HD  0.20 M.Hrs/Cum

                                          Rectangular tower




             2             F1b            Erection  and Dismantle HD  0.30 M.Hrs/Cum

                                          Square tower



             3              F2            Erection  and Dismantle L&T  0.40 M.Hrs/Cum

                                          System Stair Tower



             4              F3            Erection  and Dismantle LD                  0.10 M.Hrs/Cum


                                          or Access Scaffold Tower



             5              F4            Erection  and Dismantle Pipe  0.50 M.Hrs/Cum


                                          & Cup lock Scaffolding



             6              F5            Erection  and Dismantle Cup  0.50 M.Hrs/Cum

                                          lock  Scaffolding