Page 236 - AREA I VMGO - RELEVANT DOCUMENT
P. 236
Project Description Project Amount Source Status
Canal Lining Phase III 190,000.00 Use of Income- 100% Completed
STF
Canal Lining Phase IV 21,000.00 Use of Income- 100% Completed
STF
Construction of Water 2,000,000.00 GAA 2019 70% Complete
System
Construction of 2,000,000.00 GAA 2019 72% Complete
Perimeter Fence
Construction of Multi- 100,000.00 PTA-GRAD’N Waiting for the
purpose Hall/Old Site FUND Lumber to be
used c/o admin-
istration
Vegetable shed/nursery 200,000.00 NAFES-TF Waiting for
Ground leveling
works
Student Housing Expense- 200,000.00 Use of Income- 40% Complete
Improvement of Dormitories STF
(Habitat & Chungalao
Ladies Dorm
Improvement of the Main 500,000.00 Use of Income- 90% Completed
Gate STF
Construction of IT and Engi- 15,400,000 GAA 2018 96% Completed
neering Building
Establishment of WiFi Con- 1, 000, 000 GAA 2019
nection in the Administra-
tion Building as part of the
Automation System
Construction of the BSHRM 10, 000, 000 GAA On bidding
Building
Total 30,225,000.00
21