Page 138 - Villas at Savona Close-out Manual
P. 138

shaft from 4-feet to 6-feet, Torrent uses reaming  knives attached to the 48-inch  diameter bucket.  If a
            SoilMec is used, a 6-foot diameter flight auger is used to begin the shaft, which is changed to a 4-foot
            diameter auger after the upper excavation is  completed. In either case, the enlargement of  the upper
            portion of the excavation to 72-inches in diameter provides the working access needed to erect the
            chamber and place the gravel pack.

            It is vital to the function of the finished drainage system that a continuous 10-foot interface is achieved with
            some sort of suitable  permeable drainage material at the terminus of the excavation. As the drilling
            progresses and each load of cuttings is discharged, the composition of the drainage soils is assessed for
            suitable permeability. Optimum permeability is found in soils comprised of clean sand, gravel and small
            cobbles, with an absence of silt, clay or excessive fines. However, other materials may possess acceptable
            transmissibility, such as clean sand or decomposed granite.

            It is significant to note that the crew that completes the excavation for the systems is not the crew that will
            build the finished structures. When the drilling is completed, the drilling crew will leave the site protected by
            covering the open holes with steel plates, and constructing a berm around the immediate well site.
            Barricades and flagging are additionally utilized to protect the drilled shafts after the excavation is
            complete. A construction crew will then arrive within a day or two to finish the installation process.
            The actual construction sequence begins with pulling the plates back far enough to allow the placement of
            a setting platform over the first open boring.  The first component lowered into the excavation is the slotted
            drainage screen, connected to the lower end of the drainage pipe. The material used for the drainage pipe
            is heavy-duty ADS Highway Grade corrugated polyethylene. This HDPE drainage pipe  is  lowered into
            position, and held slightly off the bottom of the pilot-hole. The pipe is then capped and suspended by a
            chain, which has been secured to the setting platform above the excavation.

            As the fabrication progresses, the protective steel plates are pulled completely away so that there is access
            for the backfill operation. A skip loader is utilized to place the gravelpack into the entire length of the 48-
            inch pilot hole around the suspended drainage pipe.  Next, the lower perforated section of 48-inch precast
            liner for the main well is lowered into place within the enlarged 6-foot diameter excavation. Additional liner
            segments are carefully aligned and stacked in the enlarged portion of the shaft to create the settling
            chamber of the system. The last section to be placed at grade is a modified manhole cone.  The opening in
            the manhole cone is covered to prevent the accidental introduction of gravel as the upper excavation is
            backfilled with this same washed, graded aggregate.

            The trench  between the chambers of the MaxWell Plus System is excavated from the surface with a
            backhoe. A 4-inch diameter Schedule 40 PVC pipe is placed into this trench to interconnect the inlet
            structure to the main drywell settling chamber. Piping connections through the liner walls are mudded after
            the connecting pipe has been stubbed-out in the chambers.

            The assembled intake inlet for the Primary Settling Chamber is then installed. At the top of this component,
            a PVC tee is utilized to connect the anti-siphon vent to the intake screen below. The completed vented
            intake assembly is then fitted to the stubbed-out connecting pipe inside the inlet structure.

            As a good workmanship measure, a stabilizing slurry mixture is utilized to backfill the trench holding the
            connecting pipe between the chambers so that the potential for subsidence is minimized. This same slurry
            envelope is placed around all deep piping connections,  and around the cone  sections of the upper
            chambers. This material effectively encapsulates  the components, and approximates the compaction of
            native soil.  With the  chambers completed, the interior components are installed. The overflow pipe  is
            lowered into position in the main well chamber as assembly progresses.

            Each chamber is equipped with two hydrophobic floating absorbent pillows for the removal of a wide range
            of petroleum-based organic liquids. One blanket in each chamber is filled with a unique type of polymer
            plastic bead which resists the release of these constituents, even if compressed.

                                                                5
   133   134   135   136   137   138   139   140   141   142   143