was designed for a live load of about   garage evaluations are completed by   design team at the time should have
           2.4 kPa and knowing that 2’’ of asphalt   the corporation’s engineer. Ensure   checked that there was sufficient
           equates to a load of 1.2 kPa, the layer of   that structural repairs are carried   capacity, but these records may not
           asphalt would consume half of the live   out as required and under the   still be available today. If your condo
           load capacity. Structural deterioration in   supervision of an engineer. Charging   is from this era, and has a mastic/
           the garage could also have reduced the   stations often force the congregation   asphalt system installed, it is best
           capacity of the slab. Perhaps, the heavier   of these heavier vehicles in a single   to consult with the Corporation’s
           electric vehicles on this deteriorated and   bay or adjacent bays which makes the   engineer for further direction. A
           already loaded slab were the proverbial   condition of the slab in these areas   design check may be required. n
           “straw that broke the camel’s back”.     even more important.
             There are some important takeaways   4. For condos from the late 1980’s and   Sophia Rojenko, P. Eng, Project Man-
           to consider:                        earlier. Many of these garages were   ager with Synergy Partners, is a reserve
           1. If your garage has been maintained,   designed without waterproofing.   fund study and performance audit spe-
             and is structurally sound, and no   The Corporation’s engineer can   cialist  who has been practicing since
             additional loads have been added   review the drawings to try and see   2017. Sophia has a particular interest in
             to the slabs, then there shouldn’t   whether a waterproofing system was   helping condominiums get on the path
             be a concern about having electric   anticipated in the original design.   to financial success so they can be effec-
             vehicles parked in your garage.   If waterproofing was not in the   tive and vibrant communities.
           2. Make sure that part of the design   original design but was installed post
             live load has not been consumed   construction, typically the system   Shahe Sagharian, P. Eng, Senior Vice
             by the addition of a waterproofing   that was used was a thin system (ie.   President of Building Structures & Transit
             system or other loads. It is very   elastomeric, Kelmar, etc.), which is   at LEA Consulting Ltd, has been practic-
             difficult to find records of this and   a lightweight system. It is less likely   ing structural engineering since 1988.
             one must verify site conditions to   that mastic/asphalt would have   With  a  career  spanning over three de-
             ensure that it has not happened. It   been used because these systems   cades,  Shahe has been instrumental in
             is best practice to post signs for any   are thick and would not allow   designing a wide array of new structures,
             loading restrictions that result from   sufficient clearance within the garage.   as well as restoration and evaluation of
             in-service modifications.         However, it is possible in some cases   modern and historic structures.
           3. Ensure that periodic comprehensive   that mastic/ asphalt was used. The   www.lea.ca














                                      THE TRUSTED LEADER IN

                                 CONDOMINIUM MANAGEMENT
                                        IN THE GTA SINCE 1968!



                          Our experienced, professional Condominium Management Resource Team
                          is working together to protect your investment and enhance your lifestyle.







               INTEGRITY • PERFORMANCE • INNOVATION
               We invite you to join our dynamic team and many satisfied clients.
               DEL PROPERTY MANAGEMENT INC.
                416.661.3151    info@DelCondo.com
                4800 Dufferin Street, Toronto, Ontario M3H 5S9
               www.delpropertymanagement.com



 18 I CM Magazine FALL 2024                                                                                 19
   14   15   16   17   18   19   20   21   22   23   24