2/26/24, 11:10 AM Dubai Municipality initiates project to develop Dubai Creek pier, upgrade support walls
The project is set to be implemented in two phases, with the initial phase
involving the restoration of a 2.1 km stretch along the Deira side of Dubai
Creek. The site will be divided into multiple sections, and each segment will be
sequentially patterned to ensure uninterrupted docking traffic. The second
phase will cover a 2.3 km length on the Bur Dubai side.
Global Reputation: Dawoud Al Hajri, Director-General of Dubai Municipality,
stated that the project highlights Dubai Municipality's commitment to
transforming Dubai into a more attractive and innovative city by enhancing
various elements and services it offers through the strategic and sustainable
development of all coastal facilities and infrastructure in the Emirate. The goal
is to solidify Dubai's position as a global tourism hub and augment its
economic and commercial prosperity.
Al Hajri said, "The project is set to improve security and safety measures for
maritime traffic and commercial operations within Dubai Creek. As a
significant symbol of the city's growth, Dubai Creek serves as a vibrant artery
at the heart of Dubai.
Facilitating the passage of over 13,000 ships annually, it plays a key role in
fostering the economic and social prosperity of the emirate. Additionally, the
creek further supports commercial dealings with neighbouring markets in the
region."
"We have implemented several measures to mitigate the risks posed by
climate change and rising sea levels, closely monitoring changes on both
sides of the creek. Furthermore, we have conducted technical studies to
devise construction designs that can enhance the efficiency of the marine
docks on both banks.
These designs adhere to the highest global standards, ensuring the
preservation of the supporting walls' stability and safeguarding against
increased flooding during seasonal weather conditions." Al Hajri added.
Comprehensive work: The project's 14-month timeline includes the restoration
of the 2.1 km Deira pier, which involves replacement and the rehabilitation of
https://www.indianeconomicobserver.com/news/dubai-municipality-initiates-project-to-develop-dubai-creek-pier-upgrade-support-walls20240225154150/ 2/3