ution Overview

• No planning permission required
• No need for cranes or special transporters and road closures for delivery - it is rapidly assembled

onsite
• Every panel is one-man manageable and simply slots together to form a building complete with data

racks in place
• From site delivery to complete working datacentre in two or three weeks
• Built usually of 100mm walls, each of two 2mm fully galvanised and powder coated skins with

Rockwool insulation – the entire building is fire rated to typically one hour in accordance with BS476
Pt20&22. With similar constructional specimens over 20 years old still looking good and performing
well in the field, life expectancy is 25+ years
• It is lightning protected to BS EN62305 and wind resistant up to 150mph. (Suitable ground fixings are
needed to avoid sliding in hurricane conditions.)
• Physical security is paramount and the building is designed to meet LPS1175 Rating-3, Tools
Category-3 – meaning it can withstand a deliberate attempt at forced entry using bodily physical
force and tools such as axe, cold chisel, brick bolster, crow bar, lump hammer and cordless drill.