Page 2 - Engineering
P. 2

1.  GENERAL PERFORMANCE STATISTICS


                 1.1. TRACK



                 1.1.1.   PERFORMANCE OF TRACK WORKS

                    CTR UNITS :
                     Progress  of  51.529  TKM  has  been
                     achieved       against     proportionate
                     target  of  49.66  TKM  (upto  Oct‟21)
                     and annual target  of  85.14  TKM. The
                     percentage       of    performance        is
                     103.764%.


                    TRR(P) :
                     Progress  of  64.75  TKM  has  been
                     achieved       against     proportionate
                     target  of  72.92  TKM  (upto  Oct‟21)
                     and  annual  target  of  125  TKM.  The
                     percentage       of    performance        is
                     92.91%. Less progress          is  due  to
                     less supply of rails.


                    TSR(P):
                     Progress  of  17.112  TKM  has  been
                     achieved       against     proportionate

                     target  of  12.25  TKM  (upto  Oct‟21)
                     and  annual  target  of  21  TKM.  The
                     percentage       of    performance        is
                     139.69%.  Annual  target  has  been
                     achieved.


                      TRR(S) :
                     Progress  of  16.761  TKM  has  been
                     achieved       against     proportionate
                     target  of  12.25  TKM  (upto  Oct‟21)
                     and  annual  target  of  21  TKM.  The
                     percentage       of    performance        is
                     136.824%.
   1   2   3   4   5   6   7