Commissioned in the year 1995.
Hafeezp HFZ/SSP Sub Sectioning and paralleling post is used for blocks
et/SSP mainline and paralleling
Commissioned in the year 2003.
Lingamp LPI/SP 158.856 LPI/SP divide from VKB/TSS and SNF/TSS.
alli (SP) Poly Tetra Flouro Ethylene Short Neutral Section ( Arthur
Flury Make) ) available for both UP & DOWN Lines.
Commissioned in the year 2003.
Nagulap NPL/SSP 150.24 Sub Sectioning and paralleling post is used for blocks
alli (SSP) mainline and paralleling
Commissioned in the year 2008.
Shankarp SKP/SSP 139.540 Sub Sectioning and paralleling post is used for blocks
alli (SSP) mainline and paralleling
Commissioned in the year 2008.
Gullagud GGD/SSP Sub Sectioning and paralleling post is used for blocks
a( SSP) mainline and paralleling
Commissioned in the year 2009.
Vikaraba VKB/TSS 112/7-9 Vikarabad Traction Sub Station.
d (TSS) TSS is fed up to LPI/ Sectioning and Paralleling Post (46
Kms) and DRR/ Sectioning and Paralleling Post. ( 20
Kms)Commissioned in the year 2010.
Godamg GDQ/SSP Sub Sectioning and paralleling post is used for blocks
uda (SSP) mainline and paralleling
Commissioned in the year 2010.
Dharur DRR/SP 92.000 DRR/SP divide from VKB/TSS and TDU/TSS.
(SP) Poly Tetra Flouro Ethylene Short Neutral Section ( Arthur
Flury Make) ) available for both UP & DOWN Lines.
Commissioned in the year 2010.
Rukmapu RMY/SSP 82.240 Sub Sectioning and paralleling post is used for blocks
r (SSP) mainline and paralleling. Commissioned in the year
2010.
Tandur TDU/TSS 71.000 Tandur Traction Sub Station.
(TSS) TSS is fed up to DRR/ Sectioning and Paralleling Post (21
Kms) and NAW/ Sectioning and Paralleling Post. ( 19
Kms).Commissioned in the year 2011.
Mantatti MVH/SSP 62.000 Sub Sectioning and paralleling post is used for blocks
(SSP) mainline and paralleling. Commissioned in the year
2011.
Nawand NAW/SP 52.000 NAW/SP divide from MQR/TSS and TDU/TSS.
gi (SP) Poly Tetra Flouro Ethylene Short Neutral Section ( Arthur
Flury Make) ) available for both UP & DOWN Lines.
Commissioned in the year 2011.
Seram SEM/SSP 38.000 Sub Sectioning and paralleling post is used for blocks
(SSP) mainline and paralleling Commissioned in the year
2011.
Malkhaid MQR/TSS 26.000 Malkhaid Road Traction Sub Station.
Road TSS is fed up to NAW/ Sectioning and Paralleling Post
(TSS) (26 Kms) and WADI/ Sectioning and Paralleling Post. (
23 Kms) Commissioned in the year 2011.
Chittapur CT/SSP 16.000 Sub Sectioning and paralleling post is used for blocks
(SSP) mainline and paralleling
Commissioned in the year 2012.
Wadi (SP) WADI/SP 3.000 WADI/SP divide from MQR/TSS and ---/TSS ( Central
Railway).Poly Tetra Flouro Ethylene Short Neutral
Section ( Arthur Flury Make) ) available for both UP &
DOWN Lines.
Commissioned in the year 2012.