Page 12 - Engineering
P. 12

1.2.8.  IMPROVEMENT  TO  LEVEL  CROSSINGS
                   SURFACES

               Road surfaces and grades are being attended

               at LCs on a regular basis to maintain them at
               desired standards.











               1.2.9.  IMPROVEMENTS TO LC Road SURFACE BY
                   PROVIDING HARD STONE
               As  an  innovative  method  of  improving  the
               road surface, LC Nos 54, 75A & 93 on VKB-PRLI

               in  VKB-PRLI  other  LC  gates  have  been
               provided  with  sturdy/heavy/durable  material
               i.e.,  Granite  stone  bricks.  Work  in  progress  for
               10 nos of LCs.









            1.3.   BRIDGES

               1.3.1.  REBUILDING / REHABILITATION OF BRIDGES

               As part  of Rebuilding of  Bridges,  Insertion of Precast RCC boxes have been
               completed  for  10  bridges,  against  the  annual  target  of  12  Nos  during  the
               year. Progress achieved is 83% against proportionate target. The details are
               as under

                             2019-20                 2020-2021           2021-22 (Upto Nov- 21)
                       Target       Progress     Target     Progress       Target        Progress
                         17             8          15          15            12              10