Page 13 - Engineering
P. 13
Details of completed Bridges (upto Nov‟21) are as given below
S no Bridge No Location section
1 70UP 314/17-19 KZJ-BPQ
2 71UP 313/23-25 KZJ-BPQ
3 145DN 261/18-20 KZJ-BPQ
4 150DN 259/6-8 KZJ-BPQ
5 168UP 245/3-5 KZJ-BPQ
6 202UP 211/19-21 KZJ-BPQ
7 220UP 199/25-27 KZJ-BPQ
8 189DN 224/14-16 KZJ-BPQ
9 204UP 205/24-26 KZJ-BPQ
10 204DN 205/23-25 KZJ-BPQ
1.3.2. REBUILDING OF BRIDGES:
SC division has successfully completed rebuilding of bridges of old STONE
TOP / Arch culverts with new vent RCC box bridge provided for
additional vent way.
ADDITIONAL VENT AT 202 UP IN KZJ-BPQ ADDITIONAL VENT AT 204 UP & DN IN KZJ-BPQ
SECTION SECTION
The other bridge maintenance works carried out are as given below:
Proportionate
Sl. Annual Progress
No Description Target target (up to Jan 20)
(up to Jan 21)
a) Painting 71541 47694 55000
b) Oiling & greasing 140 93 93