P. 4
B Works in Progress (Rs. In '000s)
Year of Name of work PH Cost TDC Remarks
sanc
18-19 Lingampalli: Extension of platform 4 and 5 in connection PA 24993 Dec'21 1. PF Raising,Bed concrete for VDF
with Road No.5 at LPI station for accommodating 24 Completed.
coaches 2. VDF flooring Completed. Misc. works
are in progress.
18-19 Lingampally -Provision of cover over platform of 50m long PA 4900 Dec'21 Shelter work completed. Flooring works
on platform no. 2 are in progress. Telecom work
completed.
18-19 Replacement of FOB due to the poor condition of existing PA 32304 Dec'21 Removal of gangway and columns is
FOB at LINGAMPALLI completed Foundation concreting work
is in progress
19-20 Provision of 2 Lifts at Lingampalli station PA 12161 Mar'22 1.PO released. 2. Engg- Works in
progress. 3.Contract awarded for Elec.
power supply arrangements.
19-20 Provision of Chlorinators at LPI station. PA 833 Dec'21 Work is in progress
20-21 Provision of CIBs at LPI (PF: 4/5), PA 4434 Dec'21 All materials received after RDSO
inspection recently. Work in progress
2019-20 SC - Divn Improvements to passengers amenities viz lighting ,air PA 271 Dec'21 Estimate sanctioned. LOA issued on
circulators, LED signagesetc at MMTS stations w.r.t.writ petition 24.02.2021. Work is in progress.
(PIL
2020-21 Construction of Parcel Office and Trolley path at Lingampalli. PA 9997 Mar'22 New work sanctioned. Estimate under
preparation.
PA total 79625.00
Summary(Fig in 000's)
PH Completed In progress Total
TF 24700 0 24700
PA 84027 79625 163652
Total 108727 79625 188352