Page 4 - LPI
P. 4

B    Works in Progress                                                                              (Rs. In '000s)
      Year of                          Name of work                               PH        Cost         TDC                     Remarks
        sanc
       18-19 Lingampalli: Extension of platform  4 and 5 in connection            PA       24993       Dec'21     1. PF Raising,Bed concrete for VDF
               with Road No.5     at LPI station for accommodating 24                                             Completed.
               coaches                                                                                            2. VDF flooring Completed. Misc. works
                                                                                                                  are in progress.
       18-19 Lingampally -Provision of cover over platform of 50m long            PA       4900        Dec'21     Shelter work completed. Flooring works
               on platform no. 2                                                                                  are in progress. Telecom work
                                                                                                                  completed.

       18-19 Replacement of FOB due to the poor condition of existing             PA       32304       Dec'21     Removal of gangway and columns is
               FOB at LINGAMPALLI                                                                                 completed Foundation concreting work
                                                                                                                  is in progress

       19-20  Provision of 2 Lifts  at  Lingampalli station                       PA       12161       Mar'22      1.PO released. 2. Engg- Works in
                                                                                                                  progress. 3.Contract awarded for Elec.
                                                                                                                  power supply arrangements.
       19-20 Provision of Chlorinators at  LPI station.                           PA        833        Dec'21     Work is in progress
       20-21 Provision of CIBs at LPI (PF:  4/5),                                 PA       4434        Dec'21     All materials received after RDSO
                                                                                                                  inspection recently. Work in progress
      2019-20 SC - Divn Improvements to passengers amenities viz lighting ,air    PA        271        Dec'21     Estimate sanctioned. LOA issued on
               circulators, LED signagesetc at MMTS stations w.r.t.writ petition                                  24.02.2021. Work is in progress.
               (PIL
      2020-21 Construction of Parcel Office and Trolley path at Lingampalli.      PA        9997       Mar'22     New work sanctioned. Estimate under
                                                                                                                  preparation.
                                                                       PA total           79625.00
                                                                                                         Summary(Fig in 000's)
                                                                                  PH     Completed    In progress                   Total
                                                                                  TF       24700          0                        24700
                                                                                  PA       84027        79625                      163652
                                                                                 Total     108727       79625                      188352