Page 74 - ENGINEERING
P. 74
21. 2 Defective FB weld in new 10 RP rails if any
Unloaded
S Block between Rolling marks Remarks
No Sec. particulars
block section
Nil
21.3.Population of welds (SKV,FB)
weld
Station km
S Sec. PWI Sec UP/ population Total
No DN Remarks
From To From To SKV FB
1 SC-WADI SC SC SJVP 194.00 191.00 UP 83 0 83
2 SC-WADI SC SC SJVP 194.00 191.00 DN 97 39 136
3 SC-WADI SNF SJVP SNF 191.00 175.00 UP 274 80 354
4 SC-WADI SNF SJVP SNF 191.00 175.00 DN 337 40 377
5 SC-WADI LPI SNF GGD 175.00 129.00 UP 1462 2443 3905
6 SC-WADI LPI SNF GGD 175.00 129.00 DN 246 3455 3701
7 SC-WADI VKB GGD DRR 129.00 90.00 UP 1059 4155 5214
8 SC-WADI VKB GGD DRR 129.00 90.00 DN 949 2670 3619
9 SC-WADI TDU DRR KQT 90.00 47.00 UP 588 2463 3051
10 SC-WADI TDU DRR KQT 90.00 47.00 DN 573 2786 3359
11 SC-WADI SEM KQT WADI 47.00 3.00 UP 569 1271 1840
12 SC-WADI SEM KQT WADI 47.00 3.00 DN 1568 3559 5127
TOTAL 7805 22961 30766