Page 9 - ENGINEERING TEST
P. 9

1.2.4.  WORKS CARRIED OUT AT LC GATES TO IMPROVE SAFETY

                                                                                              As on 31.11.2021

            Sl.
            No         Description        Manned  Planned Completed                      Remarks

                                                                            Census has been conducted for
             1    Census                     242       110         80       80 LCs in 2021. Balance 30 LCs in
                                                                            progress.

             2    Up gradation               242        20         20       -



             3    Improvements to            242        50         30       Balance will be completed by
                  road surfaces                                             March 2022.


             4    Approach Gradients                     -          -       All the gradients are corrected to
                                             242
                                                                            IRPWM standards.


             5    Retro reflective           242         -          -       All statutory road warning boards
                                                                            provided with Retro reflective
                  boards
                                                                            type boards at all LCs.
                  Mechanical boom
                  locking                                                   All non-interlocked LCs have
             6    arrangements on            80          -          -       been provided with boom
                  non-interlocked                                           locking arrangement.
                  manned gates.


                  Mechanical sliding
             7    boom arrangements          80          -          -       All Non-interlocked LCs have
                                                                            been provided with sliding boom
                  on non-interlocked                                        arrangement.
                  manned gates.



               1.2.5.  ACTION PLAN FOR ELIMINATION OF MANNED LC’s as on 01.04.2021



                                                              Mode of elimination
                                 Interlocked/        Total
                         Sno                                                          Total
                                 Non interlocked  LCs
                                                                 ROB         RUB
                           1        Interlocked        169        43         30          73

                           2     Non interlocked       85         0          13          13
                           3           Total           254        43         43          86