Page 9 - ENGINEERING
P. 9
LC 93 in KZJ-BZA LC 12 in SC-KZJ
1.2.3. CONSTRUCTION OF RUBS
4 RUBs have been commissioned till October 2021 out of target of 28.
Progress up to Balance
S No Mode of elimination Target
31.10.2021
1 By RUB/LHS 28 4 24
7 RUBs Box casting completed & 2 LCs Box pushing in progress
Action plan for elimination of balance LCs
S No Section LC No. TDC for LC Closure
1 KZJ-BPQ 56 Nov21
2 KZJ-BZA 111 Nov21
3 KZJ-BPQ 33 Dec-21
4 KZJ-BPQ 65 Dec-21
5 KZJ-BZA 98 Jan-22
6 KZJ-BPQ 76 Jan-22
7 KZJ-BPQ 35 Feb-22
8 KZJ-BPQ 38 Feb-22
9 KZJ-BZA 115A Feb-22
10 KZJ-BZA 119 Feb-22
11 KZJ-BPQ 37 Mar-22
12 KZJ-BPQ 78 Mar-22
13 KZJ-BPQ 58 Mar-22
14 KZJ-BPQ 75 Mar-22
15 KZJ-BPQ 2 Mar-22
16 KZJ-BPQ 66 Mar-22
17 KZJ-BZA 74 Mar-22
18 KZJ-BZA 109 Mar-22